Swimming Pool installation with the least disruption

A client wanted a swimming pool with the least disruption. We set out and dug the hole in 2 days. Screeded the base on day 3.

Then we had to wait 5 days for the pool.  It arrived today and has been lowered into place.

Pipe work was installed and backfilling commenced around the pool. It is now being filled with water. We also have paving and copings to install while the pool is warming up. So within 3 weeks of starting on site the pool will be up to 29 degrees and swimmable. The paving should be completed within 4 weeks of starting on site.